'We're gonna need a bigger mallet...'

2015-06-16

Cleaving a 180 year old oak to make planks for the Gislinge Boat

On Monday morning, the next important phase in the construction of the Gislinge Boat began. During the spring, the boatbuilders had been in the woods at Vallø to select trees for the Gislinge Boat and at the start of May, an impressive 180 year old oak was delivered to the boatyard, where it lay patiently for the next few weeks as the boatbuilders began working on the keel and stems of the boat. 

The keel and stems are now almost complete, and so the boatbuilders attention has turned to the production of Gislinge Boat’s planks. Although small saw blades dating to the Viking and early Middle Ages have been found archaeologically, sawmarks have never been found on any ship timbers dating from that period. Instead of saws, mallets and wedges were used to cleave timbers and shape the planks, frames and other elements that make up the hull. Cleaving involves the use of wedges, mallets, axes and sheer muscle to split the oak along the line of its fibres, first in half, then quarters, eighths, sixteenths, and occasionally, 32-parts, which are then shaped to form the finished planks. (You can read more about the process here…)

Monday morning saw the area around the oak being roped off, as the boatbuilders began to gather the tools they needed for the day and to make the final deliberations before the cleaving could began. Working from the root end, the first cuts for the wedges were made as an axe blade was used to mark the preferred line the boatbuilders had chosen for the split. Small oak wedges were then driven into the oak along this line, forcing the first separation of the oak’s fibres. Simplistic as it sounds, this is essentially the cleaving process in a nutshell: slowly but surely, the wedges are driven further into the end of the trunk and the split begins to penetrate further along the length of the oak. 

After 15 minutes, Niels, the apprentice at the boatyard, began to remove the bark along the top of the oak, so the line of the split could be seen more clearly. Martin and Ture then began to increase the size of the oak wedges at the root end and the strikes of the rhythmic strikes of the hammer continued, broken only by the brief pauses taken to stand back and assess the progress of their work. After an hour, Ture began to insert small wedges into the line of the split along the side of the oak, gradually increasing their size as the cleaving continued. Standing atop the oak, Lene used a froe to help separate the fibres along the line of the split. 

By this stage, all of the boatbuilders were involved in the cleaving, taking turns to swing the mallets and keep an eye on the progression of the split, as the oak creaked and snapped in protest. It’s fascinating to watch the dynamic when they’re all working together on a task like this. Their focus is absolute, whether working with a mallet or axe in hand, or standing in the wings ready to step in when needed, they are observant at all times, moving around the oak, moving around each other with an almost deceptive calm: they chat, they laugh easily and often, they guide one another but all the time you can feel the tension increasing as the split slowly, inexorably works its way along the oak, one strike of the mallet after the other. 

Just two hours after they had begun, the end was almost in sight. The midsection had proved to be more stubborn than they had originally expected, slowing progress for a time, but eventually it yielded to the force of the blows. The oak began to ‘talk’ more and more as you could hear the fibres giving way within the trunk. More wedges were inserted into the side of the oak, and with a renewed energy and the support of a growing crowd of spectators, the boatbuilders continued steadily, blow after blow, until the split had finally worked its way along the length of the oak. Some fibres still held on stubbornly, so Martin and Asger took hold of either side of the oak at the root end and rocked it back and forth until it finally gave way (you can see a short clip of the big moment here…).

After a few moments of well-deserved rest and a lot of big smiles, the boatbuilders were back in action again, working on cleaving the first half down to quarters and then eighths. The cleaving process will continue for the next few weeks until the planks are finished and we’ll be posting regular updates of the progress here on the Gislinge blog. 

» Follow the project on Facebook...

» Follow the project on Instagram...

 


Created by Tríona Sørensen